Contract manufacturing for approval holders · ATA 25 & ATA 32
Start an enquiry

Compliance kit

The clauses you need before you place production in China

Most first programmes do not fail on capability. They fail on a quality agreement that never said who approves a concession, or a manufacturing agreement that never said who owns the tooling when the relationship ends. This kit is the set of clauses that closes those gaps.

What is in it

Five sections, written as usable clauses with the commentary kept separate — so your legal team can lift the text without lifting our opinion.

Section 1

Manufacturing agreement

  • Scope, part family and the approval each part hangs on
  • Drawing and specification control, including revision discipline
  • Tooling ownership, marking, storage and return on termination
  • Exclusivity — what is granted, for how long, and over which parts
  • Confidentiality, and what happens to data after the term ends

Section 2

Quality agreement

  • First article: when it is required, to which standard, who approves
  • In-process control and the sampling actually used
  • Nonconformance, concession and deviation routing
  • Change control — process, material, sub-tier and facility
  • Traceability granularity: heat, lot, process card, operator, serial

Section 3

Release document flow

  • Which document each approval basis can produce
  • Who signs, and what evidence that signature stands on
  • The record set that must exist before the signature is given
  • What to do when the receiving authority asks for more

Section 4

Recall and liability

  • Manufacturing defect and design defect — where the line sits
  • Notification windows, in hours, for containment decisions
  • Cost allocation for containment, rework and freight
  • Corrective action and how the closure is verified

Section 5

Supplier onboarding pack

  • The twelve documents to collect before the first purchase order
  • Audit rights: notice, scope, access to sub-tiers
  • What a desk audit can establish, and what it cannot
  • A one-page checklist for the first programme meeting

A page from the kit, published in full

Section 3 is the one people ask about first, so here is its core table rather than a description of it.

Release document flow — build to print
DocumentIssued bySigned byWhat it establishes
Purchase orderCustomerCustomerThe commercial instruction, including the revision
Drawing issueCustomerCustomerThe design data the part is built to
Process travellerManufacturing partnerOperator, per operationThat each step was performed as routed
Material certificateMill or stockistMaterial supplierWhat the material is, and which heat
First article reportManufacturing partnerCustomer qualityThat the process produces conforming parts
Certificate of conformityManufacturing partnerManufacturing partnerThat the units conform to the revision shipped
Release documentCustomer, under its approvalCustomerThat the part is released for installation
Packing listManufacturing partnerManufacturing partnerWhat is in the box, against which serials

Read the last-but-one row again. The release document is issued by the customer, under the customer’s approval. A manufacturing partner that offers to sign it for you is offering something it cannot lawfully give, and that is the single fastest way to disqualify a supplier.

How it is delivered

The contents are public. The full document set is sent after a short exchange, because half of its value is knowing which parts apply to your programme.

  • Editable documents, not a PDF brochure
  • Clause commentary separated from clause text
  • A one-page checklist for the first programme meeting
  • It is a working template set, not legal advice
  • Your counsel reviews it, as with any cross-border agreement
  • Quoted per programme; there is no published price

Request the full set

Two minutes of context is enough for us to send the right version.

Who you are
What you are building
Attachment

CSV, XLSX, PDF or TXT, up to 5 MB. Drawings and specifications are covered by the NDA you sign before transfer — send nothing you are not authorised to share.

We answer in writing within two working days. A determination can come back negative — that is the point of asking.